August 30, 2013 STAFF/STU

Murphy Hall renovation update – Aug. 30, 2013

The renovation of Murphy Hall is on schedule for a fall 2014 opening. Remember that construction areas are dangerous! Please stay out of the construction area, which is designated by the construction fence. Only authorized personnel are permitted to enter the construction area.

Project updates include:

  • The exterior masonry has been restored and cleaned. Most of the old windows have been removed and the new windows are being installed.
  • The interior demolition is complete. Openings in the floors have been cut for contractors to begin installing the new elevators and plumbing risers.
  • Activities for September include slate repairs and the installation of the new flat roofs. The new addition foundations have been poured and the steel framing for the additions is being erected.

Check the Murphy renovation website for progress photos and updates throughout the renovation.