Project Project Manager Tentative Schedule

Bernet masonry and slate repairs – April Skurka – May 18 – July 31
Masonry cleaning, inspection and repair – April Skurka – TBD
Kulas Auditorium – seating and other improvements – April Skurka – TBD
DeCarlo Varsity Center Fitness Room waterproofing – April Skurka – TBD
Residence hall stairwell repairs – April Skurka – TBD

Bernet waterline replacement – Gary Paoletta – May 18 – June 5
Hamlin Hall elevator modernization – Gary Paoletta – May 18 – July 1
Campion waterproofing – Gary Paoletta – TBD
SAC Chiller project, phase II – Gary Paoletta – Ongoing
Campus lighting – Gary Paoletta – Ongoing
Sutowski Fire Alarm upgrades – Gary Paoletta – May 18 – July 1
Sutowski electrical feed replacement – Gary Paoletta – TBD

Campion Hall lounge furniture – Kris Willis – July
Classroom and Library furniture – Kris Willis – TBD
Exterior signage rehabilitation – Kris Willis – TBD
Hamlin Hall common area paint and carpet – Kris Willis – July
B-wing office carpet and paint – Kris Willis – June

Hamlin boiler upgrade – Mitch Tabol – June/July
Shula boiler – Mitch Tabol – June/July

South Belvoir parking lot/Service Drive improvements – Rich Bretz – May 18 – July 1
Dolan Science Center patio replacement – Rich Bretz – May 18 – July 1
Millor tuckpointing – Rich Bretz – TBD

Sidewalk replacement – Rich Bretz  -Ongoing